A portfolio manager is analyzing a $2,000,000 venture capital investment. If the project succeeds until the end of the sixth year, the net present value (NPV) of the project is $6,587,000. The project has a 32.69 percent probability of surviving to the end of the sixth year. The expected NPV of the project is:
The project’s expected NPV is a probability-weighted average of the two possible outcomes: $6,587,000 if it is successful or the loss of the initial $2,000,000 investment if it fails. The expected NPV for the project is: (0.3269 × 6,587,000) + (0.6731 × -$2,000,000) = $807,090 |