CFAI book coporate finance question
1.Consider the two projects below. The CFs as well as the NPV and IRR for the two projects are given. For both projects, the requried rate of return is 10%.
0 1 2 3 4 NPV IRR
project1 100 36 36 36 36 14.12 16.37
project2 100 0 0 0 175 19.53 15.02
What discount rate would result in the same NPV for both projects?
A 010
B 1015.02
C 15.0216.37
D >16.37
2. Wilson Flannery is concerned that this project has multiple IRRs.
YR 0 1 2 3
CFs 50 100 0 50
How many discount produce a zero NPV for this project?
A 1, 0
B 2, 032%
C 2, 062%
D2, 092%
Please help…how to calculate these discount rates? |
|