A manufacturing company uses a machine hour rate to absorb production overheads, which were budgeted to be £130,500 for 9,000 machine hours. Actual overheads incurred were £128,480 and 8,800 machine hours were recorded. What was the total under absorption of production overheads? A £880 B £900 C £2,020 D £2,900 A |