A company operates a job costing system. Job 812 requires £60 of direct materials, £40 of direct labour and £20 of
direct expenses. Direct labour is paid £8 per hour. Production overheads are absorbed at a rate of £16 per direct
labour hour and non-production overheads are absorbed at a rate of 60% of prime cost.
What is the total cost of Job 812?
A   £240
B   £260
C   £272
D   £320

 

60+40+20+(40/8*16)+(120*60%)=272