请教F7的讲师celilia,关于construction contract

Celilia,您好!

刚听了您的第13课,关于存货和建造合同的,

里面的最后一道题,(q5,June 2006)

我不明天,在算amount due from(to) customers 时,为什么直接用题目给出的payments received?

题目中不是提到了work invoiced 吗?为什么不用 payments received÷90%呢?那10%是trade recievable.

您讲义里给出的format中的progress billings 该如何理解?

谢谢!

vickie 您好,

      Sorry for the delay.

      在construction contract中progress billing 表示收到的付款.包含received and receivable.

format中有一项是  less:progress billings 这个包含已经收到的和还应收到的(progress billings received and receivable)

 

 所以在这道题中,90%是progress billings received,10%是progress billings  receivable.应该这样解答:

gross amount due from customers:                             $m

costs to date                                                              12.5

recognised profit(1.5+1)                                              2.5

progress billings(12.6/90%)                                       (14)

due from customers                                                     1.0

TOP

谢谢您,还有问题

我明白您说的了。

1、那是不是,讲义里的答案是错误的?

讲义里的答案是:

contract cost incurred 12.5

recognised profits       2.5

payments received  (12.6)

due from customers   2.4

2、如果按您的回复里的来解这个题,那是否会在balance sheet里比答案多个 receivable 呢?

再次表示感谢!

TOP

是的.这里想说一下参考资料的问题,因为讲义是在2008年6月之前做的,所以上面的部分答案跟讲课中的新准则会有出入.所以建议在做题时答案参考最新版的练习册.讲义中讲课部分的内容是和新准则一致的.