Please explain the breakpoint of a project. Schweser note says:
"Any given project’s NPV will decline when a breakpoint is reached." &
"An increase in the after-tax cost of debt may occur at a break point."
Please explain.
作者:
ftwcfa
时间:
2011-7-11 18:40
to add insult to injury:
breakpoint is calculated as (amount of capital where component cost changes / weight of component in the WACC)