Board logo

标题: Reading 44: Capital Budgeting -LOS e, (Part 1)~ Q1-3 [打印本页]

作者: cfaedu    时间: 2008-4-4 15:36     标题: [2008] Session 11 - Reading 44: Capital Budgeting -LOS e, (Part 1)~ Q1-3

1If the calculated net present value (NPV) is negative, which of the following must be TRUE? The discount rate used is:

A)   equal to the internal rate of return (IRR).

B)   Too high.

C)   less than the internal rate of return (IRR).

D)   greater than the internal rate of return (IRR).


2
The NPV profile is a graphical representation of the change in net present value relative to a change in the:

A)   prime rate.

B)   payback period.

C)   discount rate.

D)   internal rate of return.


3
When using net present value (NPV) profiles:

A)   one should accept all mutually exclusive projects with positive NPVs.

B)   the NPV profile's intersection with the vertical y-axis identifies the project's internal rate of return.

C)   one should accept all independent projects with positive NPVs.

D)   the NPV profile's intersection with the horizontal x-axis identifies the amount of profit the project will make.



作者: cfaedu    时间: 2008-4-4 15:36

答案和详解如下:

1If the calculated net present value (NPV) is negative, which of the following must be TRUE? The discount rate used is:

A)   equal to the internal rate of return (IRR).

B)   Too high.

C)   less than the internal rate of return (IRR).

D)   greater than the internal rate of return (IRR).

The correct answer was D)

When the NPV = 0, this means the discount rate used is equal to the IRR.  If a discount rate is used that is higher than the IRR, the NPV will be negative.  Conversely, if a discount rate is used that is lower than the IRR, the NPV will be positive.


2
The NPV profile is a graphical representation of the change in net present value relative to a change in the:

A)   prime rate.

B)   payback period.

C)   discount rate.

D)   internal rate of return.

The correct answer was C)

As discount rates change the net present values change. The NPV profile is a graphic illustration of how sensitive net present values are to different discount rates. By comparison, every project has a single internal rate of return and payback period because the values are determined solely by the investment’s expected cash flows.


3
When using net present value (NPV) profiles:

A)   one should accept all mutually exclusive projects with positive NPVs.

B)   the NPV profile's intersection with the vertical y-axis identifies the project's internal rate of return.

C)   one should accept all independent projects with positive NPVs.

D)   the NPV profile's intersection with the horizontal x-axis identifies the amount of profit the project will make.


The correct answer was
C)

Where the NPV intersects the vertical y-axis you have the value of the cash inflows less the cash outflows, assuming an absence of money having a time value (i.e., the discount rate is zero). Where the NPV intersects the horizontal x-axis you have the project’s internal rate of return. At this cost of financing, the cash inflows and cash outflows offset each other. The NPV profile is a tool that graphically plots the project’s NPV as calculated using different discount rates. Assuming an appropriate discount rate, one should accept all projects with positive net present values, if the projects are independent. If projects are mutually exclusive select the one with the higher NPV at any given level of the cost of capital.






欢迎光临 CFA论坛 (http://forum.theanalystspace.com/) Powered by Discuz! 7.2