返回列表 发帖

Reading 32: Understanding the Income Statement - LOS b, (Pa

6.Net construction-in-progress that will appear on the balance sheet of SC as of December 31, 2004, is:

 

Completed Contract Method

Percentage-of-Completion Method

 

A)                              $50,000            $50,000

B)                              $50,000            $157,143

C)                              $157,143          $50,000

D)                              $250,000          $157,143

7.According to the installment method of accounting, gross profit on an installment sale is recognized:

A)   on the date of sale.

B)   on the date the final cash collection is received.

C)   in proportion to the cash collection.

D)   after cash collections equal to the cost of sales have been received.

8.An analyst has gathered the following data pertaining to Hegel Company’s construction projects, which began during 2002:

                                                                           Project 1  Project 2

Contract price                                             $420,000     $300,000

Costs incurred in 2002                                   240,000       280,000

Estimated costs to Complete                         120,000         40,000

Billed to customers during 2002                      150,000       270,000

Received from customers during 2002               90,000       250,000

If Hengel used the completed contract method, what amount of gross profit (loss) would Hengel report in its 2002 income statement for:

 

Project 1

Project 2

 

A)                                  ($20,000)      $0

B)                                  $0           ($20,000)

C)                                  ($20,000)      ($20,000)

D)                                  $0            $0

9.If Hengel used the percentage-of-completion method, what amount of gross profit (loss) would Hengel report in its 2002 income statement?

A)   $(20,000).

B)   $22,500.

C)   $40,000.

D)   $20,000.

10.Cash collection is a critical event for income recognition under the:

 

Cost-Recovery Method

Installment Method

 

A)                                     No         Yes

B)                                     No         No

C)                                     Yes       Yes

D)                                     Yes             No

答案和详解如下:

6.Net construction-in-progress that will appear on the balance sheet of SC as of December 31, 2004, is:

 

Completed Contract Method

Percentage-of-Completion Method

 

A)                              $50,000            $50,000

B)                              $50,000            $157,143

C)                              $157,143          $50,000

D)                              $250,000          $157,143

The correct answer was B)

Since completed contract method does not recognize any interim profit, the construction in progress will be recorded at $250,000. Net construction in progress under completed contract will be recorded at $50,000 [$250,000 less $200,000 (progress billings)]. The construction in progress account in the percentage of completion method will be recorded at $357,143($1 million × (250/700). Net construction in progress under percentage of completion method will be $157,143[$357,143 less $200,000 (progress billings)].

7.According to the installment method of accounting, gross profit on an installment sale is recognized:

A)   on the date of sale.

B)   on the date the final cash collection is received.

C)   in proportion to the cash collection.

D)   after cash collections equal to the cost of sales have been received.

The correct answer was C)

The installment sales method recognizes sales and COGS in proportion to cash collections

8.An analyst has gathered the following data pertaining to Hegel Company’s construction projects, which began during 2002:

                                                                           Project 1  Project 2

Contract price                                             $420,000     $300,000

Costs incurred in 2002                                   240,000       280,000

Estimated costs to Complete                         120,000         40,000

Billed to customers during 2002                      150,000       270,000

Received from customers during 2002               90,000       250,000

If Hengel used the completed contract method, what amount of gross profit (loss) would Hengel report in its 2002 income statement for:

 

Project 1

Project 2

 

A)                                  ($20,000)      $0

B)                                  $0           ($20,000)

C)                                  ($20,000)      ($20,000)

D)                                  $0            $0

The correct answer was B)

No profit is recognized until the completion of the project, however losses are recognized. Project 2 has an expected loss of $20,000.

9.If Hengel used the percentage-of-completion method, what amount of gross profit (loss) would Hengel report in its 2002 income statement?

A)   $(20,000).

B)   $22,500.

C)   $40,000.

D)   $20,000.

The correct answer was D)

Under the percentage of completion method, $40,000 of profit is recognized for project 1. 120,000 + 240,000 = 360,000 total costs; 240,000/360,000 × 60,000 estimated profit = $40,000 profit  

Project 2 is running at a $20,000 loss. If the loss can be estimated the loss must be recognized at the time it is estimated.  Total revenue for project 2 = 300,000 contract price - 320,000 total costs = -$20,000 estimated loss

40,000 (project 1) -20,000 (project 2) = $20,000 gross profit in 2002

10.Cash collection is a critical event for income recognition under the:

 

Cost-Recovery Method

Installment Method

 

A)                                     No         Yes

B)                                     No         No

C)                                     Yes       Yes

D)                                     Yes             No

The correct answer was C)

Recognition of income depends on cash collected under both methods.

TOP

返回列表