计算结果跟答案对不上
A project has the following annual cash flows
Year 0:-4662005
Year 1:22610723
Year 2:-41 072 261
Year 3:33 116 550
Year 4 : 10 000 000
which of following discount rate most likely produces the highest net present value
A:8% B 10% C 15%
下面是我的计算过程,请指点。
CF 清零
CF0=-4662005
C01=22610723
C02=-41 072 261
C03=33 116 550
C04=10 000 000
I= 8
CPT NPV=14700289.47
I=10
NPV=13660269
I=15
NPV=11435164.85
可是答案是 15% |