Contractors,INC,has contracted to build a stadium for the City.The contract price is 100million.costs are estimated to be 60million,and the time to completion is three years.Compared to the completed contract method,what effect will usingthe percentage-of-completion method most likely have on a year 2 leverage ratio and year3 cash flow from operation?
which would be lower?